You are a project manager for a construction project budgeted at $750,000. As of today, the project should be 45% completed but after reviewing the status of the scheduled tasks involved in the project it is evident that only 25% of the work has been completed. The team has spent $200,000 thus far.
GET HELP WITH YOUR ESSAY
If you need assistance with writing your essay, our professional Essay Writing Service is here to help!
DISCOUNT CODE FIRST25
ORDER THIS OR A SIMILAR PAPER NOW
You are a project manager for a construction project budgeted at $750,000. As of today, the project should be 45% completed but after reviewing the status of the scheduled tasks involved in the project it is evident that only 25% of the work has been completed. The team has spent $200,000 thus far.
Answer the two questions below:
1. Describe the formula for each equation and provide the answer
3. Determine Earned Value (EV)
4. Determine Planned Value (PV)
5. Determine Cost Performance Index (CPI)
6. Determine Schedule Performance Index (SPI)
7. Cost Variance (CV)
8. Schedule Variance (SV)
2. What does this data tell you
GET HELP WITH YOUR ESSAY
If you need assistance with writing your essay, our professional Essay Writing Service is here to help!
DISCOUNT CODE FIRST25
How It Works
Securely pay for your academic paper
Paper gets assigned to an expert tutor
Receive the complete paper via email
Team up With Your Own Writing Expert Now
Stuck with overwhelming assignments? We will take care of all your writing tasks.